• DTE Announces Gas Line Relocation Project

    Weather permitting, Miller Pipeline crews are expected to be on site, starting on Monday (1/12/26) beginning the necessary work in the areas outlined below. 

    The first phases of work will take place in the two northeastern highlighted sections.  Crews will begin working on N. Illinois and Carpenter Streets during the month of January.  The second segment of work will likely involve the boring of new pipe under I-75.  Following that work, crews will move over to the highlighted areas along Mankowski, towards the Home Depot.  The areas south of Main St, east of I-75 along S. Illinois and Ohio Streets will likely be reserved until near the end of the project.  All of this work must be completed prior to MDOT beginning their work this spring.